ISA CTEEP’s corporate structure includes its subsidiaries 100% and non-consolidated subsidiaries as shown below:


 
  Contract Deadline
(years)
Expiration Operational Status Next Tariff Review RAP
Cycle 2020/20211
(BRLmillion)
RAP  ISA CTEEP Cycle 2020/2021 (BRLmillion) Adjustment Index Share
(%)
Consolidation Transmission lines (km) Substations (MVA) Voltage (kV)
ISA CTEEP 059/2001 30 31/12/2042 Operational 2023 3,131 3,131 IPCA ISA CTEEP  100% Fully consolidated 14,295 48,822 440, 345, 230, 138, 88 e  69
IE Madeira 013/2009
015/2009
30 25/02/2039 Operational 2024 552 282 IPCA ISA  CTEEP 51% / Furnas 24,5% / Chesf 24,5% Equity equivalence
Equity equivalence
2,385 7,464 600 CC
IE Ivaí 022/2017 30 11/08/2047 Under Constrution 2023 300 150 IPCA ISA CTEEP 50% / TAESA 50% Equity equivalence 600 2,988 500 e 230
PBTE 012/2016 30 21/11/2046 Operational 2022 172 172 IPCA ISA CTEEP  100% Fully consolidated 30 N/A 345
IE Paraguaçu 003/2017 30 10/02/2047 Under Constrution 2022 121 61 IPCA ISA CTEEP 50% / TAESA 50% Equity equivalence 338 N/A 500
IE Garanhuns 022/2011 30 09/12/2041 Operational 2022 95 48 IPCA ISA CTEEP 51% / Chesf 49% Equity equivalence 633 2,100 500 e 230
Aimorés 004/2017 30 10/02/2047 Under Constrution 2022 81 41 IPCA ISA CTEEP 50% / TAESA 50% Equity equivalence 208 N/A 500
Riacho Grande 05/2021 30 31/03/2051 Under Constrution 2025 68 68 IPCA ISA CTEEP  100% Fully consolidated 31 800 345
IE Pinheiros 012/2008
015/2008
018/2008
021/2011
30 15/10/2038
09/12/2041
Operational 2024
2022
57
6
57
6
IPCA ISA CTEEP 100% Fully consolidated
Fully consolidated
Fully consolidated
Fully consolidated
1 4,200 345
IE Aguapeí 046/2017 30 11/08/2047 Operational 2023 60 60 IPCA ISA CTEEP 100% Fully consolidated 121 1,400 440
Serra do Japi 143/2001
026/2009
30 20/12/2031
18/11/2039
Operational N/A
2020
13
43
13
43

IGPM
IPCA

ISA CTEEP 100% Fully consolidated
Fully consolidated
137 2,000 230
IE Itaúnas 018/2017 30 10/02/2047 Under Constrution 2022 53 53 IPCA ISA CTEEP 100% Fully consolidated 79 1,350 345
IENNE 001/2008 30 16/03/2038 Operational 2023 53 53 IPCA ISA CTEEP 100% Fully consolidated 710 N/A 500
IEMG 004/2007
07/2020
30 23/04/2037
20/03/2050
Operational
Under Constrution
2022
2025
20
33
20
33
IPCA ISA CTEEP 100% Fully consolidated 173
172
N/A
1,600
500
345
IE Itaquerê 027/2017 30 11/08/2047 Operational 2023 52 52 IPCA ISA CTEEP 100% Fully consolidated N/A 900 It has no transmission line. Compensator voltage: 500 kV
Evrecy 020/2008
01/2020
30 17/07/2025
20/03/2050
OperationalUnder Constrution 2021
2025
13
38
13
38
IGPM
IPCA
ISA CTEEP 100% Fully consolidated
Fully consolidated
163
169
450
800
230
230
IE Tibagi2 026/2017
006/2020
30 11/08/2047
20/03/2050
Operational
Under Constrution
2023
2025
21
5
21
5
IPCA ISA CTEEP 100% Fully consolidated
Fully consolidated
17
37
500
N/A
230
230
IE Sul 013/2008
016/2008
30 15/10/2038 Operational 2024 20 20 IPCA ISA CTEEP 100% Fully consolidated
Fully consolidated
167 900 230
IE Biguaçu 012/2018 30 20/09/2048 Under Constrution 2024 41 41 IPCA ISA CTEEP 100% Fully consolidated 27 300 230
IE Itapura 042/2017
021/2018
30 11/08/2047
21/09/2048
Operational
Under Constrution
2023
2024
12
11
12
11
IPCA ISA CTEEP 100% Fully consolidated
Fully consolidated
N/A
5
250
1,200
It has no transmission line. Compensator voltage: 440 kV
It has no transmission line. Compensator voltage: 440 kV
Total           5,071 4,503            

Note: 1 RAP consider 100% of the project | 2 IE Tibagi's RAP does not consider adjustment resulting from the contractual amendment (-13.5%), approved by ANEEL's Board on 10/26/20

Click here to download the spreadsheet

Updated on April 27, 2021.